Re-covering the Stoke City FC Academy Dome
Stoke City FC’s Academy Dome is a Cover-All clear-span fabric building at the club’s training ground on Dennis Viollet Avenue, Stoke-on-Trent. The building is used year round for academy training, and by 2020 it was around 20 years old.
The problem: a failing cover
The steel frame was still sound, but the original fabric had failed. There was a large hole in the roof, the panels were discoloured, stained and torn, and water was getting into the building.
This is common with buildings of this type: the standard fabric supplied on them often doesn’t last.

A large hole in the old roof fabric, August 2020.

The old roof fabric from inside, November 2020.

Worn lower cladding on the outside of the dome.
Stage one: urgent panel replacement (December 2020)
The first priority was the worst-damaged area. We surveyed the existing panels, then designed and patterned two new PVC panels in white Mehler 8540 to suit what was on site. A four-person team removed the damaged fabric, fitted new aluminium track and pulled the new panels into it, working from MEWPs inside the building and by rope access on the roof. The knock-in flaps were then closed to make the joints watertight. The work was programmed for the week commencing 14 December 2020.

A new white panel alongside the old fabric, December 2020.
Stage two: re-covering the building (2021)
With the new panels in place, the contrast with the rest of the roof was obvious, and the club asked us to re-cover the remainder of the building. We 3D laser-surveyed the dome and brought it into CAD. We then designed and patterned the remaining eight roof panels and both gable ends.
The new cover is in Mehler 8540 PVC, white above a blue lower section in the club’s colours, and the gables carry large printed club crests. The old panels and gables were removed and disposed of, new aluminium track was fitted, and the new fabric was installed with knock-in flaps to seal the joints. The existing steel frame was retained. The re-cover was finished by November 2021.

Side elevation of the finished dome in white and club blue.

Inside the dome under the new roof.

A printed club crest on the new gable end.
A short video of the project is on YouTube:
Ongoing inspection
Since the re-cover, we have carried out inspections of the dome, including in July 2024 and June 2025. Regular inspection catches small issues early and helps the new cover reach its full service life.
Specification
- Client: Stoke City Football Club
- Location: Stoke City Academy, Stoke-on-Trent
- Structure: Cover-All clear-span fabric building (existing steel frame retained)
- Scope: 3D laser survey, design and patterning, removal and disposal of the old fabric, new aluminium track, supply and installation of new roof panels and gables
- Panels: 10 roof panels (2 in December 2020, 8 in 2021) plus 2 gable ends
- Fabric: Mehler 8540 PVC, white with blue lower section
- Graphics: printed club crests on both gables
- Fixing: new aluminium track with knock-in flaps
- Completed: by November 2021
- Aftercare: periodic inspections